°ÍÀè¹ú¼ÊÓéÀÖ³Ç NCCCO Digger Derrick Practical Course Outline
1. Chain in Circle
- When given the start signal, timing has begun. Raise the chain about 10 ft. off the ground to clear obstacles and personnel, move it over DA-2, and land the chain in DA-2.
- Once it makes contact, do not lift chain off the ground.
- Avoid contacting anything, but DA-2.
- Once the chain is under control in DA-2, the stop signal will be given.
2. Hand Signals
- You will follow four hand signals to bring the chain from DA-2 back to DA-1. This is not timed.
3. Test Weight through Corridor—Forward
- When given start signal, timing has begun. Guide the Test Weight through the corridor.
- Avoid letting the Test Weight contact anything, but keep the chain on the ground.
- Once the Test Weight is placed in DA-2, the stop signal.
- If the stop is not given this indicates the weight is not within the circle and timing continues.
- When finished, you may reposition the boom tip, but do not lift the Test Weight.
4. Test Weight through Corridor—Reverse
- When given you the start signal, timing has begun. Guide the Test Weight back through the corridor.
- All the same instructions as before apply: avoid hitting anything, keep the chain on the ground, and be sure test Weight lands in DA-3.
- Once in DA-3, the stop signal will be given.
5. Un-stow Auger
- When given the start signal, un-stow auger. This task is untimed.
- Safely un-stow the auger and contact ground in preparation to dig a hole.
6. Auger Hole
- When given the start signal, auger a hole in the ground on my mark. This task is untimed.
- Dig until flights are no longer visible and the stop signal is given.
7. Stow Auger
- When given the start signal, safely stow auger. This task is untimed.
- When ready, the proctor will assist in connecting the strap to the pin.
8. Pick up pole
- When given the start signal, pick up the pole and place securely in pole guides with the pole a few inches off the ground. Keep the pole butt within DA-4. This task is untimed.
- For safety reasons, if at any point, control of the pole is lost, the task will be stopped and your exam will end.
- If you’d like assistance in the final placement of pole in pole guides, signal the examiner.
- Once completed, the stop signal will be given.
9. Place pole in DA-5
- When given the start signal, timing has begun. Move pole into DA-5.
- Once inside DA-5, the stop signal will be given.
10. Stow Boom in Cradle
- When given the start signal, timing has begun. Stow boom and following proper secure procedures for travel.
- Once properly stowed, the stop signal will be given.